The EIA Programme

Please find listed below the revised anticipated key milestone dates for the Mooi-Mgeni River Transfer Scheme Phase 2 (MMTS-2):

1st Public Review comment of Draft Environmental Impact Report (EIR) (30 days) - 17/4/08
2nd Public Review comment period of draft EIR (14 days) - 1/6/08
Submit Final EIR to DEAT - 7/7/08
Record of Decision (3 months after submission) - 7/10/08
End of Appeal period (30 days after the ROD) - 7/11/08